May 9

Demolition Underway
|
May 25

Underpinning Helical Piers
|
July 3

Caissons Done
|
July 12

Mud Slab Void/Forms
|
July 13

Pouring Mud Slab
|
July 25

Priming Mud Slab
|
July 27

Waterproofing Mud Slab
|
August 2

Reframing Living Room
|
August 4

Structural Slab Preparations
|
August 7

Pouring Structural Slab
|
August 16

Forming Foundation Walls
|
August 16

High-tech Waterstop
|
August 18

Pouring Foundation Walls
|
August 21

Foundation Walls Stripped
|
September 3

Applying Wall Membrane
|
September 3

Slab Membrane Turned Up Edge
|
September 6

Sump Pit Keeping Groundwater at Bay
|
September 7

Drain Board and Rock Fillet
|
September 9

Backfilling
|
September 15

Basement Floor with Drain Cavity
|
September 18

Basement Floor Insulation
|
September 20

Basement Wall Framing
|
September 26

First Floor System
|
September 29

First Floor Walls
|
October 17

Second Floor System
|
October 17

Window Wells Formed
|
October 31

Second Floor Walls and Trusses
|
November 9

Front Porch Pour
|
November 9

Garage Slab Ready to Pour
|
November 13

NW with Roof
|
November 13

SW with Roof
|
November 13

SE with Roof
|
December 13

S Exterior Trim Work
|
February 18

SE with Windows, Porches and Trim
|
February 18

SW with Windows, Porches and Trim
|
February 24

Ready for Stucco
|
March 8

Installing Water and Sewer
|
March 9

Installing Dry Well
|
March 9

Low Voltage Hub
|
March 9

Main Electrical Panels
|
March 9

Water, Gas and Sewer Hub
|
March 26

Second Floor Mechanical
|
March 26

Solar System Pre-Plumbing
|
March 27

Basement Ready for Insulation
|
March 27

Busy Basement Ceiling
|
March 27

Fancy Framing in Media Room
|
March 27

Hearth Room Framing
|
March 27

Main Floor Ready for Insulation
|
March 27

Second Floor Ready for Insulation
|
April 11

Media Room Insulated with Fiberglass Exterior Walls, Cellulose Interior
Walls and Foam Floor
|
April 12

Basement Insulated
|
April 12

Living Room Insulated
|
April 12

Second Floor Insulated
|
May 8

Drywall Finishing
|
May 8

S Exterior Finished except Masonry
|
May 8

SW Exterior Finished except Masonry
|
May 8

NW Exterior Finished except Masonry
|
May 8

NE Exterior Finished except Masonry
|
May 14

Appliances and Plumbing Fixtures
|
|