701 Forest Chronology

May 9

Demolition Underway

May 25

Underpinning Helical Piers

July 3

Caissons Done

July 12

Mud Slab Void/Forms

July 13

Pouring Mud Slab

July 25

Priming Mud Slab

July 27

Waterproofing Mud Slab

August 2

Reframing Living Room

August 4

Structural Slab Preparations

August 7

Pouring Structural Slab

August 16

Forming Foundation Walls

August 16

High-tech Waterstop

August 18

Pouring Foundation Walls

August 21

Foundation Walls Stripped

September 3

Applying Wall Membrane

September 3

Slab Membrane Turned Up Edge

September 6

Sump Pit Keeping Groundwater at Bay

September 7

Drain Board and Rock Fillet

September 9

Backfilling

September 15

Basement Floor with Drain Cavity

September 18

Basement Floor Insulation

September 20

Basement Wall Framing

September 26

First Floor System

September 29

First Floor Walls

October 17

Second Floor System

October 17

Window Wells Formed

October 31

Second Floor Walls and Trusses

November 9

Front Porch Pour

November 9

Garage Slab Ready to Pour

November 13

NW with Roof

November 13

SW with Roof

November 13

SE with Roof

December 13

S Exterior Trim Work

February 18

SE with Windows, Porches and Trim

February 18

SW with Windows, Porches and Trim

February 24

Ready for Stucco

March 8

Installing Water and Sewer

March 9

Installing Dry Well

March 9

Low Voltage Hub

March 9

Main Electrical Panels

March 9

Water, Gas and Sewer Hub

March 26

Second Floor Mechanical

March 26

Solar System Pre-Plumbing

March 27

Basement Ready for Insulation

March 27

Busy Basement Ceiling

March 27

Fancy Framing in Media Room

March 27

Hearth Room Framing

March 27

Main Floor Ready for Insulation

March 27

Second Floor Ready for Insulation

April 11

Media Room Insulated with Fiberglass Exterior Walls, Cellulose Interior Walls and Foam Floor

April 12

Basement Insulated

April 12

Living Room Insulated

April 12

Second Floor Insulated

May 8

Drywall Finishing

May 8

S Exterior Finished except Masonry

May 8

SW Exterior Finished except Masonry

May 8

NW Exterior Finished except Masonry

May 8

NE Exterior Finished except Masonry

May 14

Appliances and Plumbing Fixtures